The question about the delivery time usually comes up in the final part of the quote discussion, but it determines when your production actually begins. Lead time isn’t a single number but a series of phases—and in the case of a vertical form, fill, and seal machine in a linear arrangement with auxiliary equipment It's the longest chain that counts, not the shortest. This guide breaks it down.
What Determines the Lead Time
Three factors are key. One: standard or custom—a machine from the catalog with fixed size ranges builds faster than a design tailored to your specific bag. Two: the composition of the line—a multihead weigher or checkweigher has its own build time, which either runs in parallel or extends the production chain. Three: the options you add later; every change after the order is placed resets the engineering process. The associated cost structure is listed at How much does a packaging machine cost?.
The Five Phases
The specification and quotation phase takes one to two weeks when all information is provided. Construction and assembly make up the bulk of the process: this is where the technicians assemble, wire, and test the machine. This is followed by the factory acceptance test (FAT)—a 2- to 4-hour operational test run using your film and, preferably, your product, conducted by bag size in 30-minute blocks. Next comes transportation with export documentation. Finally, on-site commissioning (SAT), during which installation, calibration, and operator training take one to two days.
| Phase | Scope | Who is sending |
|---|---|---|
| Specifications and Quote | 1 to 2 weeks | You and the builder |
| Construction and Assembly | main part | machine manufacturer |
| FAT at the factory | 1 day | together |
| Transportation | distance-dependent | carrier |
| On-site SAT | 1 to 2 days | together |
Utilities ready, running on the first day
The SAT is only brief if your site is ready: a power connection of 3 to 7 kW depending on the machine class, compressed air at 6 bar with dry air, a drain, and sufficient film storage. A missing compressed air connection or an electrical panel with insufficient capacity can cause days of delay for a machine that’s already on site—make sure to take care of this during the construction phase, not at the time of delivery.
What You Can Do to Speed Things Up
You have four key factors to consider. Send a complete specification—including the product, bag sizes, production speeds, and operating environment—all at once. Send film samples in advance so that the seal test can be conducted at the factory rather than in your production area. Schedule operator training during the SAT, because a machine without trained operators won’t produce anything. And decide on all options at once—any later expansion requires its own engineering, whereas including the same option in the order usually saves on costs.
Frequently Asked Questions
Q: How can I tell if something is off-the-shelf or custom-made?
Standard machines list size ranges, dosing principles, and speeds in the catalog; customization begins when your bag or product falls outside those parameters. Ask the manufacturer explicitly which parts of your quote come from the catalog and which are newly designed.
Q: Can I attend the FAT?
Yes, and that's a good idea: you'll see your own film and product in action and sign off on the test results. Many manufacturers now stream the test live—ask for this option if traveling is difficult.
Q: What if a component delays construction?
Request the list of critical components upon order confirmation: the weigher, the control system, and the drives determine the chain. In the event of a delay, a temporary solution might be to rent equipment rather than shut down operations—the considerations are listed at Rent or Buy a Packaging Machine.